Project stakeholders are finding it difficult to know the real-time status of who has been assigned to various stories and the status of each work item. Which of the following should the agile project manager do?
A.
Use an information radiator to help increase the transparency of work for key stakeholders.
B.
Send status updates whenever the stakeholders request them.
C.
Hold Scrum meetings more frequently to ensure stakeholders are well informed.
D.
Instruct the team to focus on their own assignments rather than the work of others.
An information radiator is a visual tool (such as a Kanban board or task board) that displays the current status of work items in real-time. It allows stakeholders and team members to see who is working on what and the progress of each story, without the need for constant status requests or additional meetings. This fosters transparency and keeps everyone informed in an agile and efficient manner.
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
thewalker
2 months, 2 weeks agoPetrevski
1 year, 3 months ago