Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMI-ACP All Questions

View all questions & answers for the PMI-ACP exam

Exam PMI-ACP topic 1 question 268 discussion

Actual exam question from PMI's PMI-ACP
Question #: 268
Topic #: 1
[All PMI-ACP Questions]

Part way through a project, several team members are in conflict over whether or not a deliverable has been properly completed. How should the agile leader reduce this conflict?

  • A. Facilitate team agreement on the definition of done (DoD) during the chartering process.
  • B. Motivate the team during Tuckman's "storming" phase.
  • C. Ensure the product owner is grooming the backlog so user stories are clearly written.
  • D. Ensure epics are broken down into smaller user stories for clarity.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
thewalker
1 week, 6 days ago
Selected Answer: A
Definition of Done (DoD): A clear and agreed-upon DoD eliminates ambiguity about what constitutes a completed deliverable. This prevents conflicts later in the project. Chartering Process: The chartering process is the initial phase of a project where the team establishes its goals, roles, and expectations. Defining the DoD during this phase sets a strong foundation for consistent understanding. B. Motivating during "storming": While motivation is important, it doesn't directly address the root cause of the conflict, which is a lack of clarity about the deliverable's completion criteria. C. Grooming the backlog: Well-written user stories are essential, but they don't necessarily define the specific criteria for a deliverable to be considered "done." D. Breaking down epics: Breaking down epics into user stories improves clarity, but it doesn't address the specific conflict about the deliverable's completion.
upvoted 1 times
...
HoatBQ
4 months ago
Selected Answer: A
A is correct.
upvoted 1 times
...
patti13
9 months, 2 weeks ago
Selected Answer: D
In my opinion, D is correct. Think about decomposition. From Mike Griffiths: "In the value-based decomposition process, we pull forward elements of the project—in the level of detail that is appropriate for the project phase we are in and how much we currently know about the project—into a format that we can work with for the next process. We then continue to refine and elaborate those elements, adding increasing levels of detail and transforming them into a format that can be further refined in subsequent processes. The end product of this process is a highly detailed deliverable that is still true to the original design objectives." A is incorrect: we are beyond the chartering process. C is incorrect: not the product owner is grooming the backlog, but the team.
upvoted 1 times
...
daichou
1 year ago
Selected Answer: C
C is correct, the conflict was happened, DoD in charter process is not appriciated
upvoted 1 times
...
Petrevski
1 year ago
Selected Answer: C
A = would be correct if the question was set: How should the agile leader AVOID this conflict? BUT, since the conflict has already happened, and the question is "How should the agile leader reduce this conflict?", in my opinion, the more suitable option here is C.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...