Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMI-ACP All Questions

View all questions & answers for the PMI-ACP exam

Exam PMI-ACP topic 1 question 267 discussion

Actual exam question from PMI's PMI-ACP
Question #: 267
Topic #: 1
[All PMI-ACP Questions]

A project team developer has been involved in a large corporate initiative that has negatively impacted team productivity on another project to which they have been assigned. How should the developer have handled this situation?

  • A. Worked as planned to meet the team's commitments and participated in other events as time permitted.
  • B. Worked extensively on the corporate initiative in order to inform the team of that effort.
  • C. Asked to be relieved of project tasks to maintain team velocity.
  • D. Have not participated in any initiative that could take focus away from the team’s project and goals.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
thewalker
1 week, 5 days ago
Selected Answer: C
Maintain Team Velocity: By asking to be relieved of project tasks, the developer ensures that the team’s velocity is not negatively impacted. This allows the team to continue meeting their commitments without the burden of an overextended team member. Focus on Priorities: This approach allows the developer to focus on the large corporate initiative without compromising the productivity and goals of the other project. Effective Resource Management: It helps in managing resources effectively by reallocating tasks to other team members who can handle them without being overburdened. Transparency and Communication: This action demonstrates transparency and proactive communication, ensuring that both project teams are aware of the developer’s capacity and can plan accordingly. Avoid Burnout: It helps in preventing burnout by not overloading the developer with too many responsibilities, which can lead to decreased performance and morale.
upvoted 1 times
thewalker
1 week, 5 days ago
A. Worked as planned to meet the team's commitments and participated in other events as time permitted: This option may lead to overcommitment and decreased productivity in both projects, as the developer might not be able to effectively manage both responsibilities. B. Worked extensively on the corporate initiative in order to inform the team of that effort: Focusing extensively on the corporate initiative without addressing the impact on the other project can lead to missed deadlines and unmet commitments. D. Have not participated in any initiative that could take focus away from the team’s project and goals: This option is not practical, as developers often need to balance multiple responsibilities. Completely avoiding participation in other initiatives may not be feasible or beneficial for career growth and organizational goals.
upvoted 1 times
...
...
zayn_1983
4 weeks, 1 day ago
Selected Answer: C
option A suggests trying to balance commitments, it does not address the potential negative impact on the team's productivity
upvoted 1 times
...
Emily87
8 months ago
Selected Answer: C
Option A (Worked as planned to meet the team's commitments and participated in other events as time permitted) may not address the negative impact on team productivity caused by the developer's involvement in the corporate initiative. Option B (Worked extensively on the corporate initiative in order to inform the team of that effort) might provide information but may not be the best approach if it hampers the team's ability to meet its commitments. Option D (Have not participated in any initiative that could take focus away from the team’s project and goals) may be a valid approach if the corporate initiative is not directly related to the team's project and goals. However, if the developer is required to be involved, open communication about the impact and seeking relief from tasks is a more proactive and collaborative approach.
upvoted 1 times
...
Petrevski
1 year ago
Selected Answer: A
A = correct
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...