Exam PMI-ACP topic 1 question 265 discussion

Actual exam question from PMI's PMI-ACP
Question #: 265
Topic #: 1
[All PMI-ACP Questions]

A new stakeholder has recently joined a project. During a meeting with the scrum master, the new stakeholder tries to understand the status of the project and the remaining tasks for completion.

How should the scrum master inform the new stakeholder?

  • A. Show the stakeholder the latest release breakdown for the project.
  • B. Invite the stakeholder to attend the next sprint review meeting.
  • C. Show the stakeholder the progress radiators for the project.
  • D. Invite the stakeholder to attend the next sprint planning meeting.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
thewalker
1 week, 6 days ago
Selected Answer: C
Progress radiators, such as burn-down charts, kanban boards, or other visual tools, offer a clear, real-time view of the project's current status and remaining tasks. These tools are designed to provide transparency and help stakeholders understand the progress without needing to attend multiple meetings. This approach allows the new stakeholder to get a quick overview of the project's progress efficiently. A. While this provides some information, it may not give a complete picture of the current status and remaining tasks. It focuses more on deliverables rather than ongoing progress. B. This is a good practice for stakeholder engagement, but it may not provide immediate information about the project's current status and remaining tasks. D. While this can help the stakeholder understand future planning, it does not address the immediate need to understand the current project status and remaining tasks.
upvoted 1 times
...
PuranDom
1 month ago
I prefer C because the question state that "the new stakeholder tries to understand the status of the project and the remaining tasks for completion." The all-remaining tasks can't be shown and project status (done items). Additionally, even though PO try to sort remaining backlog for showing future work to customer at late stage of demonstration, it is also not complete "done items = status".
upvoted 1 times
...
latigo
6 months ago
Selected Answer: C
The 1st step is showing the project Progress Radiator. Invite that stakeholder to sprint review meeting should be the next step
upvoted 1 times
...
daichou
1 year ago
Selected Answer: C
A new stakeholder, they need to know about status and progress of project in previous sprints which is showed at Progress radiators. while, the next sprint review meeting only demonstarte items in current sprint.
upvoted 4 times
...
Petrevski
1 year, 1 month ago
Selected Answer: B
B = correct
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...