Exam PMI-ACP topic 1 question 252 discussion

Actual exam question from PMI's PMI-ACP
Question #: 252
Topic #: 1
[All PMI-ACP Questions]

When working on a new product, what should an agile team do to ensure alignment with external stakeholders?

  • A. Hold a kick-off meeting to assign roles.
  • B. Review the project vision statement.
  • C. Ask the product owner for a detailed product-specification document.
  • D. Work with the scrum master to ensure that agile principles are followed.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
thewalker
2 weeks, 1 day ago
Selected Answer: B
Reviewing the project vision statement helps the agile team ensure alignment with external stakeholders by providing a clear understanding of the product’s goals and objectives. This ensures that everyone, including the stakeholders, is aligned on the overall purpose and direction of the product.
upvoted 1 times
thewalker
2 weeks, 1 day ago
A. Hold a kick-off meeting to assign roles. Reason: While assigning roles is important, it does not ensure alignment with external stakeholders on the project's goals and vision. C. Ask the product owner for a detailed product-specification document. Reason: Detailed specifications can be useful, but they may not provide the high-level alignment and shared understanding that a vision statement offers. Agile methodologies also emphasize flexibility over rigid specifications. D. Work with the scrum master to ensure that agile principles are followed. Reason: Ensuring adherence to agile principles is important for the team's process, but it does not directly address alignment with external stakeholders on the project's vision and goals.
upvoted 1 times
...
...
PuranDom
1 month ago
simply B
upvoted 1 times
...
Petrevski
1 year, 1 month ago
Selected Answer: B
B =correct
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...