Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMI-ACP All Questions

View all questions & answers for the PMI-ACP exam

Exam PMI-ACP topic 1 question 248 discussion

Actual exam question from PMI's PMI-ACP
Question #: 248
Topic #: 1
[All PMI-ACP Questions]

A project team is currently working on sprint seven of a release that is estimated to require twelve sprints to complete. The team has reviewed the stories for this sprint and discovered that it will require rework from previous sprints.

What should the scrum master do?

  • A. Ask the product owner to revisit the scope of the release and revise it so that the team can keep the current commitment schedule.
  • B. Ask the team to find a workaround so that they can continue with the current project management plan.
  • C. Advise the team to continue working on the sprints as the release plan has been set.
  • D. Ask the team to estimate the amount of rework needed so that adjustments can be made to both the project and release plan.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
thewalker
2 months, 3 weeks ago
Selected Answer: D
Rework is a reality in Agile projects, and it's essential to address it as soon as it's discovered. By asking the team to estimate the rework, the Scrum Master ensures that the project and release plan remain realistic and achievable. This approach allows for transparency and informed decision-making, maintaining a balance between quality and progress.
upvoted 1 times
thewalker
2 months, 3 weeks ago
A. Ask the product owner to revisit the scope of the release and revise it so that the team can keep the current commitment schedule. While revisiting the scope might be necessary later, the team first needs to understand the scope of the rework. Adjusting the release plan should come after that estimation. B. Ask the team to find a workaround so that they can continue with the current project management plan. A workaround might introduce technical debt and quality issues. It's better to address the root cause and handle the rework properly. C. Advise the team to continue working on the sprints as the release plan has been set. Ignoring the rework could lead to further issues down the line and compromise the quality of the product. Adjusting plans to accommodate necessary rework is a more sustainable approach.
upvoted 1 times
...
...
Petrevski
1 year, 3 months ago
Selected Answer: D
D = correct (the most logical option)
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...