The lead developer informed the team that they have learned of some possible integration challenges in creating customer dashboards using the architecture the team has chosen. What should an agile practitioner do?
A.
Conduct an architectural spike immediately to decide how the functionality will be determined.
B.
Work with the product owner to avoid the risk by determining if their requirements could be met with reporting or a similar functionality.
C.
Continue the priority defined by the product owner on the backlog for the functionality they determined to be the highest priority.
D.
Identify this as a risk, decide on the response, and prioritize spike to determine the solution on the product backlog.
Acknowledge the Risk: The lead developer's information highlights a potential integration challenge, which is a risk to the project's success.
Risk Management: Agile practices emphasize risk management. The team needs to acknowledge the risk, assess its impact, and decide on a response.
Architectural Spike: An architectural spike is a short, focused effort to investigate and validate a technical approach. In this case, a spike would help the team understand the integration challenges and explore potential solutions.
Prioritization: The spike should be prioritized on the product backlog to ensure it's addressed promptly. This allows the team to make informed decisions about the project's direction.
A. Conduct an architectural spike immediately to decide how the functionality will be determined: While a spike is necessary, it shouldn't be done immediately without considering the risk and its impact.
B. Work with the product owner to avoid the risk by determining if their requirements could be met with reporting or a similar functionality: This might be a viable solution, but it's important to first understand the nature of the integration challenges and explore all options.
C. Continue the priority defined by the product owner on the backlog for the functionality they determined to be the highest priority: Ignoring the risk and continuing with the current plan could lead to significant problems later in the project.
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
thewalker
2 months, 3 weeks agothewalker
2 months, 3 weeks agoPetrevski
1 year, 3 months ago