A project just kicked off and management's expectation is to ensure that the deliverable of the first iteration helps the marketing team present the product prototype to potential customers. What should the project manager do?
A.
Increase the details of the work breakdown structure (WBS) to minimize errors and delays
B.
Split the backlog into phases to ensure that the key features are delivered first
C.
Ask the sponsor to prioritize some functionalities of the product
D.
Identify the minimum functionality required for the product
D. Identify the minimum functionality required for the product.
Explanation:
This approach aligns with the concept of Minimum Viable Product (MVP), which focuses on delivering the essential features that provide value to customers and stakeholders. By identifying the minimum functionality required, the project team can work towards delivering a version of the product that can be presented to potential customers quickly, gather feedback, and iterate based on the feedback received.
upvoted 1 times
...
This section is not available anymore. Please use the main Exam Page.PMP Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
victory108
7 months, 3 weeks agoJamrock
8 months, 1 week ago