Exam PMI-ACP topic 1 question 227 discussion

Actual exam question from PMI's PMI-ACP
Question #: 227
Topic #: 1
[All PMI-ACP Questions]

Which option describes how risk should be managed in an agile project?

  • A. Since using an agile methodology minimizes risk in project management, the project team can focus on delivering business value over managing risk.
  • B. Project team members would each be responsible for identifying and managing risks for the individual user stories they have been assigned.
  • C. All stakeholders are responsible for identifying risks during standups, retrospectives, and other team meetings.
  • D. The product owner is responsible for identifying risks and entering them into the backlog so that their mitigation can be prioritized.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
thewalker
2 months, 3 weeks ago
Selected Answer: C
Collaborative Risk Management: In agile projects, risk management is a collaborative effort involving all stakeholders. This approach ensures that risks are identified and addressed promptly by leveraging the collective knowledge and experience of the entire team. Continuous Identification: Risks are continuously identified during regular agile ceremonies such as standups, retrospectives, and other team meetings. This ongoing process helps in early detection and mitigation of risks, reducing their potential impact on the project. Shared Responsibility: By making risk management a shared responsibility, the team can ensure that no single point of failure exists. This collective approach enhances the team's ability to manage risks effectively and adapt to changes quickly.
upvoted 1 times
thewalker
2 months, 3 weeks ago
A. Since using an agile methodology minimizes risk in project management, the project team can focus on delivering business value over managing risk: While agile methodologies can help in managing risks, it does not eliminate the need for active risk management. Ignoring risk management can lead to unforeseen issues that could derail the project. B. Project team members would each be responsible for identifying and managing risks for the individual user stories they have been assigned: This approach can lead to fragmented risk management and may overlook risks that affect the project as a whole. A collaborative approach ensures comprehensive risk management.
upvoted 1 times
thewalker
2 months, 3 weeks ago
D. The product owner is responsible for identifying risks and entering them into the backlog so that their mitigation can be prioritized: While the product owner plays a crucial role in prioritizing the backlog, risk identification should not be solely their responsibility. Involving all stakeholders ensures a more thorough and effective risk management process.
upvoted 1 times
...
...
...
janojano
9 months, 4 weeks ago
Selected Answer: C
B is not a bad answer, but C seems more aligned with all the Agile events that represent opportunities for all stakeholders to bring forward risks.
upvoted 1 times
...
melki_zedek
1 year ago
I will go for C. In an agile project, risk management is a shared responsibility among all team members and stakeholders.
upvoted 1 times
...
Petrevski
1 year, 3 months ago
Selected Answer: B
B = correct (the most logical option according to me)
upvoted 2 times
Petrevski
1 year, 2 months ago
A = Agile methodology maximizes the value, but that doesn't mean minimizes the importance of managing the risk C = The stakeholders do not attend standups, retros... they attend reviews D = The whole team is responsible for identifying risks
upvoted 1 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted