Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMI-ACP All Questions

View all questions & answers for the PMI-ACP exam

Exam PMI-ACP topic 1 question 221 discussion

Actual exam question from PMI's PMI-ACP
Question #: 221
Topic #: 1
[All PMI-ACP Questions]

At an iteration review, the product owner indicated that the work delivered did not meet expectations. The project team is surprised.

How should this situation have been prevented?

  • A. The team should have reviewed the definition of done prior to the iteration review.
  • B. The testers should have ensured that test cases accurately reflected the product owner's expectations.
  • C. The team should have conducted more demonstrations with the product owner during the iteration.
  • D. The product owner should have provided clearer explanations during the planning meeting.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
tungthitcho
2 months, 1 week ago
Selected Answer: D
I go for D. Due to prevent keyword. Review DoD is must when implement tasks then A is incorrect. Of course no role in agile then B is incorrect. I think that if the team want to conduct more demonstrations they should think about iteration length
upvoted 1 times
...
thewalker
2 months, 3 weeks ago
Selected Answer: C
Frequent Demonstrations: Conducting regular demonstrations with the product owner throughout the iteration ensures continuous feedback. This practice helps in aligning the team's work with the product owner's expectations and allows for timely adjustments. Early Detection of Misalignment: Regular check-ins and demonstrations help in identifying any misalignment between the team's work and the product owner's expectations early in the process, reducing the risk of surprises at the iteration review. Improved Communication: Frequent interactions with the product owner foster better communication and understanding, ensuring that the team is always aware of the product owner's requirements and any changes in expectations.
upvoted 1 times
...
PuranDom
3 months ago
Selected Answer: D
I go for D. Big question mark on the situation is, does team say work complete without checking DoD ? Rather telling yes above thing, more suitable situation in this case is following Option-D. PO didn't explained/wrote enough level of things, as a result, it caused an unhappy situation (no match expectation arose at demo) in my opinion.
upvoted 1 times
...
yassoraa88
3 months, 2 weeks ago
Selected Answer: A
the product owner is part of creating the definition of done, so reviewing it before the demo ensures that the team meets the product owner expectations
upvoted 2 times
...
ImGonnaPassIt
10 months, 2 weeks ago
Selected Answer: A
definition of done (A) is the key word and it comes before iteration planning, I think
upvoted 2 times
ImGonnaPassIt
7 months, 2 weeks ago
Nope. It must be D.
upvoted 1 times
...
...
melki_zedek
1 year ago
Selected Answer: A
A. Reviewing the definition of done prior to the iteration review could have been a crucial step to ensure alignment between the delivered work and the product owner's expectations.
upvoted 2 times
...
Petrevski
1 year, 3 months ago
Selected Answer: D
D = correct There's one review meeting (demonstration) in Scrum per iteration (sprint). The best way to ensure that developers delivered the increment as expected is to feed them with all of the necessary information during the planning meeting.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...