Exam PMI-ACP topic 1 question 218 discussion

Actual exam question from PMI's PMI-ACP
Question #: 218
Topic #: 1
[All PMI-ACP Questions]

A project team has a senior subject matter expert (SME) who is comfortable with data integration. The SME is not inclined to perform regression testing because the SME feels that performing regression testing is more of a junior duty.

What should the scrum master do?

  • A. Explain to the SME the importance of being a team player, that the tasks are assigned by the scrum master, and work should not be refused.
  • B. Acknowledge that the SME has a valid point from an efficiency point of view and will perform better staying as a specialist.
  • C. Leverage a separate testing team altogether to assist with all testing to ensure consistent results.
  • D. Explain to the team the importance of reducing team size by reducing specializations and bottlenecks and that every team member plays an equal part.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
thewalker
2 weeks, 3 days ago
Selected Answer: D
Reducing Specializations and Bottlenecks: Emphasizing the importance of cross-functional skills within the team helps in reducing dependencies and bottlenecks. This approach ensures that the team can handle various tasks without being overly reliant on specific individuals. Equal Contribution: Highlighting that every team member plays an equal part fosters a collaborative environment. It encourages team members to take on different roles and responsibilities, which is essential in Agile methodologies. Team Cohesion: By explaining the importance of shared responsibilities, the scrum master can help the SME understand that their contribution to tasks like regression testing is valuable for the overall success of the project.
upvoted 1 times
thewalker
2 weeks, 3 days ago
A. Explain to the SME the importance of being a team player, that the tasks are assigned by the scrum master, and work should not be refused: This approach is too authoritative and may not foster a collaborative team environment. It could lead to resentment and reduce team morale. B. Acknowledge that the SME has a valid point from an efficiency point of view and will perform better staying as a specialist: While specialization can be efficient, it goes against the Agile principle of cross-functional teams. It can also create bottlenecks and dependencies. C. Leverage a separate testing team altogether to assist with all testing to ensure consistent results: This option introduces additional dependencies and can slow down the process. It also contradicts the Agile principle of having a self-sufficient team capable of handling all aspects of development.
upvoted 1 times
...
...
Petrevski
1 year, 1 month ago
Selected Answer: D
D = correct
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.