Question #: 213
Topic #: 1
[All PMI-ACP Questions]

In companies where decision making is driven by data analytics and unknown variables are addressed, what advantages does agile project execution offer over a predictive approach?

  • A. A formalized agile approach offers controlled flexibility in dealing with unknown variables in a manner that adds business value.
  • B. Agile is focused only on digital transformation project management, whereas a predictive approach focuses on traditional "brick and mortar" projects.
  • C. The agile formal change management system is better able to deal with unknown variables.
  • D. Agile is relativity new; therefore, it is inherently more aligned with data-analytic-based efforts.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
thewalker
2 months, 3 weeks ago
Selected Answer: A
The correct answer is A. A formalized agile approach offers controlled flexibility in dealing with unknown variables in a manner that adds business value. Here’s why: Controlled Flexibility: Agile methodologies are designed to be adaptive and iterative, allowing teams to respond to changes and unknown variables effectively. This flexibility is crucial in environments driven by data analytics where new insights can emerge frequently. Business Value: Agile focuses on delivering incremental value through continuous feedback and improvement, ensuring that the project remains aligned with business goals and can adapt to new data and insights.
upvoted 1 times
thewalker
2 months, 3 weeks ago
Options B, C, and D contain inaccuracies: B: Agile is not limited to digital transformation projects; it can be applied to a wide range of project types, including traditional ones. C: While agile does have change management practices, the key advantage is its flexibility rather than a formal change management system. D: Agile’s alignment with data-analytic-based efforts is due to its iterative nature and adaptability, not merely because it is relatively new.
upvoted 1 times
...
...
PuranDom
3 months, 1 week ago
Selected Answer: A
B. Agile is focused only on digital transformation project management... -> upper description is wrong C. The agile formal change management system is better --> this is also wrong point able to deal with unknown variables --> this part is also depend on situation, so not correct D. inherently more aligned with data-analytic-based efforts ---> also wrong take wrong point one by one, remaining option is A.
upvoted 1 times
...
Petrevski
1 year, 3 months ago
Selected Answer: A
A = correct
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...