Exam PMI-ACP topic 1 question 211 discussion

Actual exam question from PMI's PMI-ACP
Question #: 211
Topic #: 1
[All PMI-ACP Questions]

Halfway through the execution of an agile project, a retrospective meeting is held. One of the team members believes that the actual time and cost to complete the work has consistently been greater than what was originally estimated.

Which of the following activities should be performed next?

  • A. The product owner should reduce the scope of the project so that the items delivering the highest business value can be completed.
  • B. The team should perform a spike to conduct research on their technical solutions and prove their viability.
  • C. The team should consolidate small stories into larger ones so that there are less work items to be estimated.
  • D. The team should reevaluate time and cost estimates to reflect the latest understanding of the work effort.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
thewalker
2 weeks, 4 days ago
Selected Answer: D
The best answer here is D. The team should reevaluate time and cost estimates to reflect the latest understanding of the work effort. Here's why: Addressing Inaccurate Estimates: The team member's observation points to a potential issue with the initial estimates. Re-evaluating them is crucial to ensure future estimates are more accurate and realistic. Learning from Experience: Agile methodologies encourage continuous improvement. By analyzing why estimates were off, the team can identify areas for improvement in their estimation process. Improving Velocity: Accurate estimates are essential for maintaining a consistent velocity and delivering value predictably.
upvoted 1 times
thewalker
2 weeks, 4 days ago
Why the other options are less ideal: A. The product owner should reduce the scope of the project so that the items delivering the highest business value can be completed: While reducing scope might be necessary in some cases, it's not the primary solution. The focus should be on improving the estimation process to ensure accurate planning. B. The team should perform a spike to conduct research on their technical solutions and prove their viability: Spikes are useful for exploring technical unknowns, but they don't directly address the issue of inaccurate estimates. C. The team should consolidate small stories into larger ones so that there are less work items to be estimated: Consolidating stories might make estimation easier, but it can also make it harder to track progress and adapt to changes.
upvoted 1 times
...
...
Petrevski
1 year, 1 month ago
Selected Answer: D
D = correct
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.