Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMI-ACP All Questions

View all questions & answers for the PMI-ACP exam

Exam PMI-ACP topic 1 question 209 discussion

Actual exam question from PMI's PMI-ACP
Question #: 209
Topic #: 1
[All PMI-ACP Questions]

A new project is scheduled to begin next month. The project manager has had plenty of time to review and plan all the activities and has adopted the best approach for the project and the organization.

Which action did the project manager most likely take when choosing the approach?

  • A. They most likely used a process that was successfully used for other projects; what has worked before is less likely to fail.
  • B. They most likely discussed the best approach for this project with the team and will adapt and tailor the approach periodically by reviewing and verifying the scope with the customer.
  • C. They most likely requested an increase in the management reserve; this will help the project manager to be more flexible during change requests and risk response activities.
  • D. They most likely implemented a predictive approach; this approach might limit the freedom of making changes but secures the project from unknown risks.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
thewalker
2 months, 3 weeks ago
Selected Answer: B
The best answer here is B. They most likely discussed the best approach for this project with the team and will adapt and tailor the approach periodically by reviewing and verifying the scope with the customer. Here's why: Collaboration and Adaptability: Agile project management emphasizes collaboration and adaptability. A successful project manager will involve the team in choosing the approach, ensuring buy-in and understanding. They will also be flexible and willing to adjust the approach as needed based on feedback from the team and the customer. Customer Focus: The project manager's primary goal is to deliver value to the customer. Regularly reviewing and verifying the scope with the customer ensures the project stays aligned with their needs and expectations.
upvoted 1 times
...
Petrevski
1 year, 3 months ago
Selected Answer: B
B = correct
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...