A new project manager is planning an information security project for a company that resides in different countries.
What is the first step the project manager should take to gather customer requirements?

  • A. Conduct a stakeholder analysis to identify how regional policies may influence needs
  • B. Request relevant stakeholders to conduct an analysis and reach consensus independently
  • C. Conduct a project scope review workshop with relevant stakeholders
  • D. Conduct project planning meetings in one location with relevant stakeholders
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
victory108
8 months ago
Selected Answer: A
A. Conduct a stakeholder analysis to identify how regional policies may influence needs
upvoted 1 times
...
Aish_
8 months, 2 weeks ago
Selected Answer: A
Understanding the diverse needs and requirements of different regions is essential. Conducting a stakeholder analysis is a crucial first step because it helps identify and categorize stakeholders, including representatives from different countries, who will be impacted by the project.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago