A new project manager is planning an information security project for a company that resides in different countries. What is the first step the project manager should take to gather customer requirements?
A.
Conduct a stakeholder analysis to identify how regional policies may influence needs
B.
Request relevant stakeholders to conduct an analysis and reach consensus independently
C.
Conduct a project scope review workshop with relevant stakeholders
D.
Conduct project planning meetings in one location with relevant stakeholders
Understanding the diverse needs and requirements of different regions is essential. Conducting a stakeholder analysis is a crucial first step because it helps identify and categorize stakeholders, including representatives from different countries, who will be impacted by the project.
upvoted 2 times
...
This section is not available anymore. Please use the main Exam Page.PMP Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
victory108
8 months agoAish_
8 months, 2 weeks ago