exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 701 discussion

Actual exam question from PMI's PMP
Question #: 701
Topic #: 1
[All PMP Questions]

A project manager is assigned to a new project. The project is for a new product that the company wants to launch as soon as possible to test market readiness. The project is part of a large business transformation, and the objective is to open delivery channels for the new product.

Which delivery approach should the project manager recommend?

  • A. A predictive approach with an experienced project team.
  • B. An adaptive approach with clearly defined user stories.
  • C. An adaptive approach with loosely defined large epics.
  • D. A predictive approach with clear acceptance criteria.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
KennyMuffins
8 months, 3 weeks ago
Selected Answer: B
Between B or C. But I chose B because I doubt it would be possible to begin work with loosely define large epics, the team would lost as to what work to be done.
upvoted 1 times
...
Abdelmonm
8 months, 3 weeks ago
Selected Answer: C
Given the dynamic nature of launching a new product and the need to test market readiness quickly, the project manager should recommend an adaptive approach. Specifically, option C, an adaptive approach with loosely defined large epics, aligns with the flexibility required for such projects. This allows the team to adapt to changing market conditions and customer needs during the development process. A focus on large epics provides a high-level view of the project's scope while allowing for iterative and incremental development, enabling the team to respond swiftly to emerging requirements and market feedback.
upvoted 1 times
Abdelmonm
8 months, 3 weeks ago
B. An adaptive approach with clearly defined user stories. This option aligns with Agile principles, allowing the project team to work incrementally, prioritize features based on market needs, and respond quickly to changes. Clear user stories provide specific, actionable requirements that can be delivered in short iterations, contributing to a faster time-to-market.
upvoted 1 times
...
...
UppersquareCapital
9 months, 3 weeks ago
Selected Answer: C
C. An adaptive approach with loosely defined large epics. An adaptive (or agile) approach is well-suited for projects where requirements may evolve, and there's a need for flexibility and responsiveness to changing market conditions. Loosely defined large epics allow for incremental and iterative development, making it easier to adapt to emerging requirements and customer feedback. This approach is more aligned with the dynamic nature of the project, helping the team to deliver value quickly and make adjustments based on market responses.
upvoted 1 times
...
Only12go
1 year ago
Selected Answer: B
B. An adaptive approach with clearly defined user stories. This option aligns well with the goal of launching the new product quickly to test market readiness. It allows for a more structured and incremental development process, making it easier to manage and prioritize work based on well-defined user stories. This approach is often associated with Agile methodologies, which are well-suited for fast-paced product development and market testing.
upvoted 1 times
...
victory108
1 year ago
Selected Answer: B
B. An adaptive approach with clearly defined user stories
upvoted 1 times
...
Aish_
1 year, 2 months ago
Selected Answer: B
An adaptive approach, such as Agile or Scrum, is well-suited for projects with dynamic requirements and a need for rapid delivery. By using clearly defined user stories, the project team can prioritize and deliver the most critical features first, allowing for early product releases and faster time-to-market. Option C (Adaptive approach with loosely defined large epics) is not ideal as loosely defined large epics may not provide the necessary clarity and focus needed for rapid development and timely delivery.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago