Question #: 498
Topic #: 1
[All PMP Questions]

The project charter was just approved and the project sponsor has given permission to proceed with the project. The program manager has confirmed that one of the requested key resources is also needed on another project at the same time. This will affect project delivery.
What should the project manager do?

  • A. Pay overtime to key resource to get the work done outside of working hours
  • B. Have a meeting with project manager of the other project to find a resource optimization solution that works for both projects
  • C. Speak with the client to see if the project delivery deadline can be delayed due to resource availability
  • D. Talk to the program manager and about prioritizing this project over other projects so the key resources are available
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
victory108
7 months, 4 weeks ago
Selected Answer: B
B. Have a meeting with project manager of the other project to find a resource optimization solution that works for both projects
upvoted 1 times
...
SteAle
9 months, 2 weeks ago
Selected Answer: B
B. Have a meeting with project manager of the other project to find a resource optimization solution that works for both projects
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel