An organization has historically executed most projects using a predictive approach. The organization now wants to change over to an agile approach. Which strategy will be useful to effectively help prepare the organization for this change?
A.
Create a task force of executives who will monitor agile projects on a daily basis.
B.
Add multiple layers of managers who will be accountable for the agile execution.
C.
Improve organizational readiness by addressing impediments to agile in the organization.
D.
Take a big bang approach of moving the whole organization to agile at once.
Agile transformation should be executed with a big-bang approach. It should be a smooth transitioning by removing impediments and bringing the org up to speed on the new way of working
upvoted 1 times
...
This section is not available anymore. Please use the main Exam Page.PMP Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
victory108
7 months, 4 weeks agoSteAle