exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 493 discussion

Actual exam question from PMI's PMP
Question #: 493
Topic #: 1
[All PMP Questions]

During the last sprint review, the mam stakeholder complained that the product was missing many features they had been expecting The project team argued that every increment met the acceptance criteria and was approved by the mam stakeholder The cost performance index (CPI) of the project is 1 15 and the schedule performance index (SPI) is 1.43 What should the project manager do?

  • A. Ask the project team to perform the modifications since the project budget and schedule can support them.
  • B. Ask the stakeholder to submit a change request to increase the budget and time for the modifications requested.
  • C. Explain to the stakeholder that since the acceptance criteria for every increment were met the project can be closed.
  • D. Analyze the reason for the gap in understanding with both sides and negotiate a solution.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
victory108
7 months, 4 weeks ago
Selected Answer: D
D. Analyze the reason for the gap in understanding with both sides and negotiate a solution
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago