Question #: 486
Topic #: 1
[All PMP Questions]

During the planning stage of a project the project manager realizes that a standard stakeholder engagement approach will not suffice. One of the client representatives, who is not a key decision maker, is extremely opinionated. This client representative could become a roadblock to progress due to their perceived level of authority during meetings.
How should the project manager handle this moving forward?

  • A. Ask that only key decision makers attend the project meetings.
  • B. Update the project schedule to cater to this particular stakeholder.
  • C. Allocate time to gain buy-in from the stakeholder prior to key decision meetings.
  • D. Update the risk register to consider the possible project impacts.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
victory108
7 months, 4 weeks ago
Selected Answer: C
C. Allocate time to gain buy-in from the stakeholder prior to key decision meetings
upvoted 1 times
...
SteAle
9 months, 2 weeks ago
Selected Answer: C
C seems to be the only logical answer
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.