exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 480 discussion

Actual exam question from PMI's PMP
Question #: 480
Topic #: 1
[All PMP Questions]

During the execution of a project within an operations function, the project manager encounters scope changes and a delay in the delivery of critical tasks.
How should the project manager address this situation?

  • A. Communicate the concerns to the project management office (PMO) during the weekly project reports
  • B. Call for a team meeting to decide if the changes should be included
  • C. Initiate the change request to modify the scope and adjust the timelines
  • D. Conduct an impact analysis and present the results to the steering committee for approval
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
wittycroc
1 month, 1 week ago
Selected Answer: B
D is not fully correct. Impact analysis is fine but approval from steering committee?? It works be CCB.
upvoted 1 times
...
tonybuivannghia
8 months, 4 weeks ago
Selected Answer: D
We need to analysis the impacts first, then request for approving.
upvoted 1 times
...
nicknamesdx
11 months, 3 weeks ago
I'd like to go with C
upvoted 1 times
...
odylec
1 year, 4 months ago
Selected Answer: B
Why not first discuss this with the team and if they don't find the problem or a better solution make the request?
upvoted 1 times
...
victory108
1 year, 7 months ago
Selected Answer: D
D. Conduct an impact analysis and present the results to the steering committee for approval
upvoted 1 times
...
SteAle
1 year, 9 months ago
Selected Answer: D
The PM should conduct an impact analysis first.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago