During the design phase, a project manager realizes that the project will benefit from using adaptive tools. The effectiveness of this approach has been proven in past projects inside the organization. What should the project manager do first?
A.
Update project documents to include adaptive tools and artifacts and plan the first iterative session
B.
Contact the project sponsor and request new team members who are familiar with adaptive projects
C.
Confirm team capabilities before introducing adaptive tools and artifacts to the project
D.
Freeze the design stage and look for an external resource to run iterative design at extra cost
C. Confirm team capabilities before introducing adaptive tools and artifacts to the project
upvoted 2 times
...
This section is not available anymore. Please use the main Exam Page.PMP Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.