exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 456 discussion

Actual exam question from PMI's PMP
Question #: 456
Topic #: 1
[All PMP Questions]

During the closing process, the project manager learns that one deliverable is not meeting customer expectations.
How should the project manager proceed?

  • A. Ask the customer to issue a change request with the information to analyze and provide a solution
  • B. Review the deliverable requirements, check the customer approval criteria, and proceed accordingly
  • C. Meet with the customer to reach agreement on the scope of the deliverable that will satisfy both parties
  • D. Contact the project sponsor and ask for help in negotiating the closing of the project with the customer
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
462729f
2 days, 3 hours ago
Selected Answer: B
During the closing process, the project manager must verify that all deliverables meet the agreed-upon requirements and customer expectations. PMBOK recommends validating project deliverables against documented acceptance criteria to determine whether the concern is valid or if the deliverable has already been formally accepted. This approach ensures objective decision-making rather than immediately negotiating or escalating the issue. PMBOK Key Processes Referenced: Validate Scope (Ensuring Deliverables Meet Requirements) Control Quality (Verifying Deliverables Before Closing) Close Project or Phase (Ensuring Formal Acceptance Before Closure)
upvoted 1 times
...
Jordarlu
1 week, 5 days ago
Selected Answer: B
Before doing option C, I think B should be done first
upvoted 1 times
...
RomanPorcupine
2 months, 2 weeks ago
Selected Answer: C
Initially I went for B but then I think C is correct. The PM has already learned that one deliverable is not meeting customer expectations, this means the Pm has reviewed the deliverable requirements and the acceptance criteria. Reaching a mutual agreement is what the PM needs to do at this point.
upvoted 1 times
...
nealmukundan
6 months, 1 week ago
Selected Answer: B
B. Review the deliverable requirements, check the customer approval criteria, and proceed accordingly
upvoted 1 times
...
Kim222
6 months, 1 week ago
Selected Answer: C
B does not meet customers.
upvoted 1 times
...
ju3504
8 months, 3 weeks ago
Selected Answer: C
My answer is C. PM have to meet customer.
upvoted 2 times
...
victory108
1 year, 5 months ago
Selected Answer: B
B. Review the deliverable requirements, check the customer approval criteria, and proceed accordingly
upvoted 1 times
...
SteAle
1 year, 7 months ago
Selected Answer: B
B. Review the deliverable requirements, check the customer approval criteria, and proceed accordingly
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago