exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 456 discussion

Actual exam question from PMI's PMP
Question #: 456
Topic #: 1
[All PMP Questions]

During the closing process, the project manager learns that one deliverable is not meeting customer expectations.
How should the project manager proceed?

  • A. Ask the customer to issue a change request with the information to analyze and provide a solution
  • B. Review the deliverable requirements, check the customer approval criteria, and proceed accordingly
  • C. Meet with the customer to reach agreement on the scope of the deliverable that will satisfy both parties
  • D. Contact the project sponsor and ask for help in negotiating the closing of the project with the customer
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
RomanPorcupine
2 weeks ago
Selected Answer: C
Initially I went for B but then I think C is correct. The PM has already learned that one deliverable is not meeting customer expectations, this means the Pm has reviewed the deliverable requirements and the acceptance criteria. Reaching a mutual agreement is what the PM needs to do at this point.
upvoted 1 times
...
nealmukundan
4 months, 1 week ago
Selected Answer: B
B. Review the deliverable requirements, check the customer approval criteria, and proceed accordingly
upvoted 1 times
...
Kim222
4 months, 1 week ago
Selected Answer: C
B does not meet customers.
upvoted 1 times
...
ju3504
6 months, 3 weeks ago
Selected Answer: C
My answer is C. PM have to meet customer.
upvoted 2 times
...
victory108
1 year, 3 months ago
Selected Answer: B
B. Review the deliverable requirements, check the customer approval criteria, and proceed accordingly
upvoted 1 times
...
SteAle
1 year, 5 months ago
Selected Answer: B
B. Review the deliverable requirements, check the customer approval criteria, and proceed accordingly
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago