Exam PMP topic 1 question 445 discussion

Actual exam question from PMI's PMP
Question #: 445
Topic #: 1
[All PMP Questions]

A project manager is leading an in-house company project in its very early stages. This current project is similar to another project that ended a year ago.
What should the project manager do to analyze the involved stakeholders?

  • A. Lower the priority of stakeholder engagement as the stakeholders already have knowledge of this kind of project
  • B. Use lessons learned from the previous project as a guide for the current project's stakeholder register
  • C. Refer to the stakeholder register from the previous project as it was similar to the current project
  • D. Document in the risk register that the current project may have different stakeholders than the previous project
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Kim222
7 months, 4 weeks ago
Selected Answer: B
Just because the projects are similar does not mean the stakeholders are the same.
upvoted 1 times
...
Bruce_Liu
1 year, 3 months ago
Selected Answer: C
C is the most direct response.
upvoted 1 times
...
[Removed]
1 year, 5 months ago
Selected Answer: C
C makes better sense. Lesson learned not necessary covers the stakeholder register.
upvoted 1 times
...
victory108
1 year, 8 months ago
Selected Answer: B
B. Use lessons learned from the previous project as a guide for the current project's stakeholder register
upvoted 3 times
...
SteAle
1 year, 9 months ago
Selected Answer: B
B. Use lessons learned from the previous project as a guide for the current project's stakeholder register
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel