A project manager is leading an in-house company project in its very early stages. This current project is similar to another project that ended a year ago. What should the project manager do to analyze the involved stakeholders?
A.
Lower the priority of stakeholder engagement as the stakeholders already have knowledge of this kind of project
B.
Use lessons learned from the previous project as a guide for the current project's stakeholder register
C.
Refer to the stakeholder register from the previous project as it was similar to the current project
D.
Document in the risk register that the current project may have different stakeholders than the previous project
B. Use lessons learned from the previous project as a guide for the current project's stakeholder register
upvoted 1 times
...
This section is not available anymore. Please use the main Exam Page.PMP Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Kim222
7 months, 4 weeks agoBruce_Liu
1 year, 3 months ago[Removed]
1 year, 5 months agovictory108
1 year, 8 months agoSteAle
1 year, 9 months ago