During the course of a project, the project manager's immediate director is communicating directly with the client to approve changes without the project manager's knowledge. This is causing confusion in the project team where the scope is changing in the background, but only being mentioned in project meetings.
How should the project manager handle this?
ea4e1f8
2 weeks, 5 days agoParamak
1 month agotonybuivannghia
2 months agoBruce_Liu
7 months, 4 weeks agojosephsafiran
8 months, 1 week agocb4a6c4
9 months, 1 week agoodylec
9 months, 1 week agoUncle_Lucifer
10 months, 2 weeks agovictory108
1 year agoTONYJAVI
1 year, 1 month agoSteAle
1 year, 2 months ago