During the course of a project, the project manager's immediate director is communicating directly with the client to approve changes without the project manager's knowledge. This is causing confusion in the project team where the scope is changing in the background, but only being mentioned in project meetings.
How should the project manager handle this?
462729f
4 months, 3 weeks agoea4e1f8
10 months, 2 weeks agoParamak
10 months, 4 weeks agotonybuivannghia
11 months, 3 weeks agoBruce_Liu
1 year, 5 months agojosephsafiran
1 year, 6 months agocb4a6c4
1 year, 6 months agoodylec
1 year, 7 months agoUncle_Lucifer
1 year, 8 months agovictory108
1 year, 10 months agoTONYJAVI
1 year, 11 months agoSteAle
2 years ago