During the course of a project, the project manager's immediate director is communicating directly with the client to approve changes without the project manager's knowledge. This is causing confusion in the project team where the scope is changing in the background, but only being mentioned in project meetings.
How should the project manager handle this?
ea4e1f8
2 months, 3 weeks agoParamak
3 months, 1 week agotonybuivannghia
4 months, 1 week agoBruce_Liu
10 months agojosephsafiran
10 months, 2 weeks agocb4a6c4
11 months, 2 weeks agoodylec
11 months, 2 weeks agoUncle_Lucifer
1 year agovictory108
1 year, 3 months agoTONYJAVI
1 year, 3 months agoSteAle
1 year, 4 months ago