Question #: 433
Topic #: 1
[All PMP Questions]

The change control board (CCB) rejects a change request submitted by a subject matter expert (SME). The SME refuses to accept this rejection and does not want to continue the project without the change.
What should the project manager have done to avoid this situation?

  • A. Requested that the sponsor approved the change request first
  • B. Assessed the change's overall impact to the project before submission
  • C. Ensured that the change request was aligned with the project scope
  • D. Submitted the change request directly to the CCB
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
victory108
8 months ago
Selected Answer: B
B. Assessed the change's overall impact to the project before submission
upvoted 1 times
...
SteAle
9 months, 3 weeks ago
Selected Answer: B
Impact analysis is always the first step
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.