In the beginning of project execution, the project manager finds out that a key resource will be unavailable for two weeks, which could cause a delay to the schedule. What should the project manager do first?
A.
Assign the tasks to another resource, and ask the resource to work double shifts
B.
Update the schedule to reflect the project's changes in duration
C.
Ask human resources (HR) for a replacement, and update the risk register
D.
Update the resource management plan and resource allocation chart accordingly
D. Update the resource management plan and resource allocation chart accordingly
upvoted 2 times
...
This section is not available anymore. Please use the main Exam Page.PMP Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
victory108
8 months agoSteAle
9 months, 3 weeks ago