exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 418 discussion

Actual exam question from PMI's PMP
Question #: 418
Topic #: 1
[All PMP Questions]

A vendor supplying a piece of specialized equipment for a project has reported the potential for a delivery delay due to a technical issue with the sub-supplier. To stay on schedule, the vendor proposed replacing the sub-supplier's component with a similar part that is different from the one that is stipulated in the project specifications.
What should the project manager do next?

  • A. Accept the proposed replacement in order to keep procurement activities on track
  • B. Insist on using the component per the project specifications and air freight the equipment to mitigate the delay
  • C. Instruct the vendor to use the part that is compliant with the project specifications and update the schedule
  • D. Consult with a subject matter expert (SME) to see if the proposed change is acceptable
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
kayyaly
7 months, 3 weeks ago
Selected Answer: D
D is correct
upvoted 1 times
...
SteAle
9 months, 3 weeks ago
Selected Answer: D
I would go with D. Expert judgment is one of the tools used in 'Direct and Manage Project Work' which submits CRs to Integrated Change Control Process
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago