A company is about to start a complex research project. Due to the level of uncertainty, the project manager recommends the use of a hybrid approach; however, the organization only has experience with predictive projects.
How can the project manager strategize the use of a hybrid approach to the organization?

  • A. Submit a notification to the project team confirming they will be using a hybrid approach on the project.
  • B. Send a letter to the project management office (PMO) requesting to use a hybrid approach.
  • C. Create a project change request to execute the project using a hybrid approach.
  • D. Present the benefits of a hybrid approach to key stakeholders to get their support.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
victory108
8 months, 1 week ago
Selected Answer: D
D. Present the benefits of a hybrid approach to key stakeholders to get their support
upvoted 1 times
...
SteAle
10 months ago
Selected Answer: D
By presenting the benefits of a hybrid approach to key stakeholders, the PM will get their buy-in and support which is very important during the transition phase
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.