An external project manager is managing the construction of new corporate offices for a large company. The project management plan states that it is necessary to contract a highly trained external resource to revise and validate an important project component. The client has rejected hiring the external resource because of the high cost, even though it is within the project budget.
What should the project manager do to resolve this issue?

  • A. Try to accomplish the task internally by leveling resources from other projects.
  • B. Ask the client for a meeting and explain that the task will not be performed.
  • C. Evaluate the consequences and meet with the client to explain the possible scenarios.
  • D. Hire the resource in order to achieve the project objectives.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
victory108
8 months, 1 week ago
Selected Answer: C
C. Evaluate the consequences and meet with the client to explain the possible scenarios
upvoted 1 times
...
SteAle
10 months ago
Selected Answer: C
The customer needs to be informed about the impact
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago