exam questions

Exam PMI-RMP All Questions

View all questions & answers for the PMI-RMP exam

Exam PMI-RMP topic 1 question 55 discussion

Actual exam question from PMI's PMI-RMP
Question #: 55
Topic #: 1
[All PMI-RMP Questions]

While preparing for a project review meeting with leadership, the project team analyzes and checks its scope activities and discovers missing requirements. The project risk manager decides to hire a subcontractor to fulfill these newly discovered requirements.
What risk strategy did the project risk manager use?

  • A. Avoid
  • B. Transfer
  • C. Accept
  • D. Mitigate
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Linkedin_Dario_Conde
4 weeks, 1 day ago
Selected Answer: B
B is correct because a subcontrator was hired to carry out the work
upvoted 1 times
...
Sooraj_Balakrishnan
5 months, 4 weeks ago
Selected Answer: C
The additional scope is to be executed without any change. So the risk is now an issue. Irrespective of whether the additional scope will be executed by the Project team directly or through a subcontractor, the risk has been accepted.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago