A project manager is leading a team that is geographically dispersed. The team needs to collaborate and finalize the monthly reports. Occasionally, meetings occur during the weekends due to the time differences. Team members have expressed that they do not want to work on the weekends.
What should the project manager do?
JerryMag4
3 days, 8 hours ago462729f
3 weeks, 5 days agorockyslav
5 months, 1 week agoKim222
7 months agoAditech
11 months, 3 weeks agoKennyMuffins
1 year, 1 month agoAbdelmonm
1 year, 2 months ago125bb38
1 year, 2 months agoOnly12go
1 year, 5 months agoDavid983
1 year, 5 months agovictory108
1 year, 6 months agoAish_
1 year, 7 months agoTONYJAVI
1 year, 8 months agorandomname123
1 year, 8 months agoaqz_111
1 year, 9 months agoJamrock
1 year, 7 months ago