Actual exam question from PMI's PMP
Question #: 574
Topic #: 1
[All PMP Questions]

A project manager finished reviewing the project deliverables for the current iteration with the customer. A new key stakeholder who just joined the customer's team, complains that the results do not provide the capabilities the business anticipated.
What should the project manager do to address this issue?

  • A. Create a change request and update the scope management plan
  • B. Conduct stakeholder identification and a project objectives review session
  • C. Update the stakeholder list and fix the deliverables
  • D. Update the project management plan and lessons learned
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
wittycroc
1 month ago
Selected Answer: C
Stakeholder should be added to stakeholder register as PM does not need to start a conduct stakeholder identification process. To address the issue team need to fix it.
upvoted 1 times
...
victory108
7 months, 1 week ago
Selected Answer: B
B. Conduct stakeholder identification and a project objectives review session
upvoted 1 times
...
Aish_
8 months, 2 weeks ago
Selected Answer: B
This option involves revisiting the stakeholder identification process and reviewing the project objectives with the new key stakeholder. This will help ensure that all stakeholders' expectations and needs are properly understood and aligned with the project deliverables. By conducting this session, the project manager can address any misunderstandings and discrepancies, and work towards a common understanding of the project's scope and objectives.
upvoted 3 times
...
sarfaraz_khan
10 months, 1 week ago
The project manager should choose option B: Conduct stakeholder identification and a project objectives review session. By conducting stakeholder identification, the project manager can gather information about the new key stakeholder's role, responsibilities, and expectations. This will help in understanding their perspective and concerns regarding the project deliverables.
upvoted 2 times
...
cwilson91
10 months, 1 week ago
Per chatgpt: "By conducting stakeholder identification, the project manager can ensure that all relevant stakeholders are identified and their expectations are understood. This includes the newly joined key stakeholder who expressed dissatisfaction with the deliverables. The project manager should engage in a dialogue with the stakeholder to gain a clear understanding of their expectations and concerns. Simultaneously, the project manager should review the project objectives to ensure they align with the stakeholder's expectations. This review session will allow the project manager to identify any gaps or misalignments between the deliverables and the anticipated capabilities."
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago