An organization is about to start a multiphased project. Due to strict regulations, some of the phases must be completely planned in advance. However, other phases allow for more flexibility and experimentation on scope and schedule. The sponsor wants to pursue the project objectives as planned, but also wants to accommodate new information and changes as the project progresses.
Which project management approach should the project manager select for this project?

  • A. Hybrid
  • B. Incremental
  • C. Agile
  • D. Phased
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
GabMonterey
2 weeks, 2 days ago
Selected Answer: A
A since this requires both predictive and agile approach
upvoted 2 times
...
PMNoel
2 months, 2 weeks ago
Selected Answer: A
A. Hybrid
upvoted 1 times
...
Alizade
3 months ago
Selected Answer: A
The correct answer is: A. Hybrid
upvoted 1 times
...
victory108
6 months, 2 weeks ago
Selected Answer: A
A. Hybrid
upvoted 1 times
...
Thirukj
6 months, 2 weeks ago
Answer is C
upvoted 1 times
...
TBT_1
6 months, 2 weeks ago
Selected Answer: A
Regulations are involved, so A a hybrid approach will help address both the issues
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago