exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 170 discussion

Actual exam question from PMI's PMP
Question #: 170
Topic #: 1
[All PMP Questions]

While monitoring a project at a work site, the project manager notices that the site team's work breaks have increased by a few minutes every week.
How should the project manager approach this?

  • A. Dismiss some of the workers for failing to adhere to the break policy
  • B. Issue a formal written warning to all hourly workers for their break tardiness
  • C. Have a meeting with the team to discuss the issue and propose solutions
  • D. Reduce payment to the workers due to their extended breaks
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
djgdgaf
8 months ago
Selected Answer: C
Discuss with the team first, before you start writing warnings. Lowest level.
upvoted 1 times
...
Lucky_Cindy
1 year ago
Selected Answer: C
Have a meeting with the team
upvoted 1 times
...
victory108
1 year, 4 months ago
Selected Answer: C
C. Have a meeting with the team to discuss the issue and propose solutions
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago