While monitoring a project at a work site, the project manager notices that the site team's work breaks have increased by a few minutes every week. How should the project manager approach this?
A.
Dismiss some of the workers for failing to adhere to the break policy
B.
Issue a formal written warning to all hourly workers for their break tardiness
C.
Have a meeting with the team to discuss the issue and propose solutions
D.
Reduce payment to the workers due to their extended breaks
C. Have a meeting with the team to discuss the issue and propose solutions
upvoted 1 times
...
This section is not available anymore. Please use the main Exam Page.PMP Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
djgdgaf
8 months agoLucky_Cindy
1 year agovictory108
1 year, 4 months ago