A project team member, who is inexperienced in system development work is not performing well. Currently, there are no other staff members available who are qualified to complete the work.
What should the project manager do?

  • A. Assess the team member's development requirements and arrange for the team member to receive training.
  • B. Seek approval from the project sponsor to use some of the project budget reserve to hire a new resource.
  • C. Work with the functional manager to determine an incentive for the team member to complete the project.
  • D. Request a substitute for the team member with a new resource who is more skilled in system development work.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
kavikris
2 weeks, 5 days ago
Selected Answer: D
The PM should request for a substitute, If the team member needs 6 months to gain knowledge the project should be stopped? or rescheduled? doesnt make sense
upvoted 1 times
...
Lucky_Cindy
1 year, 2 months ago
Selected Answer: A
A is correct
upvoted 1 times
...
victory108
1 year, 4 months ago
Selected Answer: A
A. Assess the team member's development requirements and arrange for the team member to receive training
upvoted 1 times
...
AbbasTaki
1 year, 6 months ago
Selected Answer: A
The project manager should first assess the team member's development requirements. This will help the project manager to identify the areas where the team member needs additional training. Once the project manager has identified the team member's development requirements, they can then arrange for the team member to receive training in these areas.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago