Actual exam question from PMI's PMP
Question #: 201
Topic #: 1
[All PMP Questions]

Several components of an expensive manufacturing project have been returned by the customer. The customer is complaining that the quality of the components is poor and is concerned that, as a result, their products will be returned due to quality issues. The project manager is certain that quality has been maintained.
How should the project manager communicate with the customer to help assure them that the project has produced quality products?

  • A. Show the customer the tolerance and control limits.
  • B. Show the customer sample results from the current batch.
  • C. Show the customer a sample history of quality.
  • D. Show the customer the quality control measurements.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
kavikris
2 weeks, 6 days ago
Selected Answer: A
The main point in this question is about the conflict, customer says the deliverables are not of quality and the project manager is certain they meet quality standards. Most likely reason is the customer is not aware of or overlooked the acceptable tolerance or variability. For example, if the material has to be 1 mm thickness, and it is 0.95 mm the customer may say it doesnt meet quality whereas project manager knows that 5% variability range should be accepted as per agreement. In this case it is about showing the customer the tolerance and control limits
upvoted 1 times
...
Lucky_Cindy
1 year, 2 months ago
Selected Answer: D
D. Show the customer the quality control measurements
upvoted 1 times
...
Asakthi
1 year, 4 months ago
A. Show the customer the tolerance and control limits.
upvoted 1 times
...
victory108
1 year, 5 months ago
Selected Answer: D
D. Show the customer the quality control measurements
upvoted 2 times
...
SteAle
1 year, 5 months ago
Selected Answer: D
The quality control measurements document the results of Control Quality activities and demonstrate compliance with the quality requirements.
upvoted 3 times
...
cwilson91
1 year, 6 months ago
Selected Answer: C
Isn't it C? By presenting a sample history of quality, the project manager can demonstrate the consistency and reliability of the project's manufacturing processes. This approach provides tangible evidence of the project's commitment to quality and can help alleviate the customer's concerns. Showing the customer the tolerance and control limits, sample results from the current batch, or the quality control measurements may not address the customer's perception of poor quality and may not provide a broader context or historical perspective.
upvoted 1 times
Acumen88
1 year, 6 months ago
This is a case of dispute; the customer already got the product but contesting that several components are below the agreed quality standard. The response is to show the customer the quality control measurements. D.
upvoted 3 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago