A software project using an agile approach is facing quality issues with every release, generating many production problems. What should the project manager do to fix the problem and improve the quality?
A.
Use the retrospective meeting to better understand the root cause of the quality problems and put together a plan with the team to address the problems
B.
Hire an external company to add an additional layer of testing, making sure that the final product is well inspected before releasing
C.
Create a reward system granting incentives to the team members who are able to catch more defects
D.
Seek extra funding approval with the sponsor to replace junior team members for more experienced ones
Selected Answer: A
A. Use the retrospective meeting to better understand the root cause of the quality problems and put together a plan with the team to address the problems
A. Use the retrospective meeting to better understand the root cause of the quality problems and put together a plan with the team to address the problems
upvoted 4 times
...
This section is not available anymore. Please use the main Exam Page.PMP Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Asakthi
8 months, 2 weeks agovictory108
11 months ago