A project manager is managing a project with a hybrid approach and has requested a senior team member to perform a quantitative risk analysis. The team member responds that they do not have the knowledge to perform such an analysis.
What should the project manager do?
betterthanyesterday
1 month agoOnly12go
1 year, 2 months agoLoan
1 year, 3 months agoLoan
1 year, 3 months agoMuntadher
1 year, 5 months agovictory108
1 year, 7 months ago