exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 138 discussion

Actual exam question from PMI's PMP
Question #: 138
Topic #: 1
[All PMP Questions]

A project manager for a technologically complex engagement reviews the key project indicators with the main stakeholders on a regular basis. During one of the meetings, the project sponsor explains that they are using the project manager's risk register as a way to communicate about the project at the executive level.
How should the project manager ensure that project risks are reported accurately in the risk register?

  • A. Update the risks in the risk management plan
  • B. Review the risks throughout project execution
  • C. List the project risks identified in the kick-off meeting
  • D. Plan to update the risks at project closure
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
WhiteTable
8 months ago
Selected Answer: B
Option B
upvoted 1 times
...
AbbasTaki
11 months ago
Selected Answer: B
B. Review the risks throughout project execution
upvoted 2 times
...
victory108
11 months ago
Selected Answer: B
B. Review the risks throughout project execution
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago