exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 129 discussion

Actual exam question from PMI's PMP
Question #: 129
Topic #: 1
[All PMP Questions]

In a time-critical construction project, a misunderstanding occurred between the supervisor and the technician. The misunderstanding turned into a major conflict and the technician has complained to the project manager that they cannot continue to work under the supervisor any longer. The supervisor cites the technician's poor performance as the reason for the conflict.
How should the project manager resolve the problem?

  • A. Use a direct, collaborative approach with the technician and supervisor
  • B. Provide a just-in-time training to the technician to improve their skill set
  • C. Replace the technician with a high performing resource as time is critical
  • D. Talk to the supervisor to tone down their approach and attitude
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Mamoonpk
3 weeks, 5 days ago
Selected Answer: D
how A? they have conflict how they will go with collaborative approach
upvoted 1 times
...
Muntadher
5 months ago
Selected Answer: A
A most fit
upvoted 1 times
...
victory108
7 months ago
Selected Answer: A
A. Use a direct, collaborative approach with the technician and supervisor
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago