In analyzing a project for monthly status reporting, the project manager notices that the schedule performance index (SPI) is 0,75 and the cost performance index
(CPI) is 1,25. The project manager must provide the first project status review soon and wants to emphasize that the project is under control.
How should the project manager report the project status to key stakeholders?

  • A. Prepare a detailed presentation for stakeholders on earned value including how it is calculated and the project's current earned value results
  • B. Report that the project is behind schedule but that an additional experienced resource can be added to stay within schedule and maintain the budget
  • C. Perform a detailed root cause analysis utilizing a pareto chart and fishbone diagrams to demonstrate that the project is under control
  • D. Report that the project is not tracking as expected, but is still under control since the next project milestone is over a month away
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
sweety433
3 weeks ago
SPI <1 which means it is behind the schedule. CPI > 1 which means UNDER the budget. We can have new resource with extra budget to ensure we deliver the project on time
upvoted 1 times
...
sweety433
3 weeks ago
Selected Answer: B
SPI <1 which means it is behind the schedule. CPI > 1 which means over the budget. We can have new resource with extra budget to ensure we deliver the project on time
upvoted 1 times
...
DavidTri
2 months, 2 weeks ago
as the question info, SPI = 0.75 mean project is behind schedule and CPI = 1.25 mean project under budget so PM can add more resource to help team to rich to ontrack and monitor the project budget make sure it is under control
upvoted 1 times
...
buvana
6 months ago
D. Report that the project is not tracking as expected, but is still under control since the next project milestone is over a month away
upvoted 1 times
...
EfaChux
6 months, 3 weeks ago
Selected Answer: C
Root cause analysis will help him under why the project is being delayed so he can find a solution to the delay problem
upvoted 1 times
...
Prathi09051982
9 months, 3 weeks ago
Selected Answer: B
We have a CPI value greater than 1, which means we are spending less cash than originally estimated. This presents us with an opportunity to allocate the excess cash towards bringing the project on schedule, especially since our SPI currently stands at 0.75.
upvoted 2 times
...
adingmaki
11 months, 3 weeks ago
Selected Answer: B
IT'S B! READ PMBOK6th!
upvoted 1 times
...
ParthaPinku
1 year ago
The most effective way for the project manager to communicate the status, keeping in mind the need to emphasize control over the project, would be D. Report that the project is not tracking as expected, but is still under control since the next project milestone is over a month away.
upvoted 1 times
...
Goku_PMP
1 year ago
Selected Answer: A
The project manager must provide the first project status review soon and wants to emphasize that the project is under control. How should the project manager report the project status to key stakeholders?
upvoted 1 times
...
victory108
1 year ago
Selected Answer: B
B. Report that the project is behind schedule but that an additional experienced resource can be added to stay within schedule and maintain the budget
upvoted 1 times
...
miggykurkova
1 year ago
CPI >1 means we have money SPI < 1 means we are late acc. to schedule So I can use my money with adding resource and then balance the schedule
upvoted 3 times
...
Aish_
1 year, 1 month ago
Selected Answer: B
SPI value shows that its behind schedule. CPI value shows that project is under budget. PM can decide to add additional resource with the budget and bring back project on schedule. That means do crashing.
upvoted 3 times
...
SteAle
1 year, 2 months ago
Selected Answer: C
Founding out the root cause of the delay (SPI<1) should help the PM to show that the project is under control
upvoted 1 times
adingmaki
11 months, 3 weeks ago
Finding the root cause of an issue shows that the PM is under control? Really?
upvoted 1 times
...
...
kevzzz
1 year, 2 months ago
Selected Answer: B
SPI @ .75 means you are only getting 0.75 cents per dollar spent or you are behind schedule. CPI of 1.25 means that you are under budget so you can hire that extra person to get the schedule back on track.
upvoted 2 times
...
rknowles
1 year, 3 months ago
Can someone please explain why C is the correct answer. Using these reporting tools don't seem to show that the project is under control?
upvoted 1 times
AstridN
1 year, 2 months ago
I'm deeply lost
upvoted 1 times
...
...
AbbasTaki
1 year, 3 months ago
Selected Answer: C
C is the correct answer
upvoted 1 times
...
noppy
1 year, 3 months ago
Selected Answer: C
I think C is correct answer.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...