A project’s requirements baseline is established and approved. A stakeholder then submits a new requirement through the change control process.
How can the business analyst determine the impact on existing requirements?

  • A. Use time-boxing to defer the new requirement.
  • B. Review the requirements traceability matrix.
  • C. Update the use case documentation.
  • D. Perform a stakeholder analysis
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
AlphaD
Highly Voted 1 month ago
B. Reviewing the requirements traceability matrix. The requirements traceability matrix is a tool that links the project requirements to their origin, rationale, and associated deliverables. It provides a comprehensive view of the relationships between different requirements and other project artifacts such as business objectives, use cases, test cases, and design documents.
upvoted 5 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago