The business analyst is planning an approach to formally manage updates to requirements that may be requested by stakeholders. What should the business analyst do?

  • A. Document changes as they occur.
  • B. Obtain approval from the project sponsor.
  • C. Develop a change control process.
  • D. Hold firm on scope and reject changes.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
AlphaD
1 month ago
C. Develop a change control process. To formally manage updates to requirements, the business analyst should develop a change control process. This process outlines the steps and procedures for requesting, reviewing, approving, and implementing changes to requirements.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago