The project team is early in the development phase of a new product. The project will need to be completed on a tight timeline and with a lean budget. What should the team do to reduce the risk of rework?
A.
Organize a new elicitation workshop.
B.
Perform a Pareto analysis on the requirements.
C.
Validate the requirements before continuing with development.
D.
Ask the project sponsor to prioritize the requirements.