The stakeholders for a newly approved project are subject matter experts who are very knowledgeable in the client’s business and will provide the project requirements. The project team scheduled separate sessions with each subject matter expert to identify and prioritize the requirements.
Which technique is being used?
AlphaD
1 month ago