Question #: 182
Topic #: 1
[All PMI-PBA Questions]

For a large, highly complex project with significant risk, which elicitation technique should be used to analyze input to and output from the product?

  • A. Interface analysis
  • B. Risk analysis
  • C. System analysis
  • D. Dependency analysis
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Ngunhucho
1 month, 3 weeks ago
Selected Answer: B
B. Risk analysis
upvoted 1 times
...
AlphaD
1 year, 6 months ago
A - Interface analysis
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted