Question #: 350
Topic #: 1
[All PMP Questions]

An organization is transitioning from a predictive to an agile approach.
What should the project manager do to ensure that the agile approaches will bring about significant change?

  • A. Obtain full management support
  • B. Identify the organization's key clients
  • C. Learn as much as possible about the organization
  • D. Conduct agile training for the team members
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
AP2023S
Highly Voted 1 year, 6 months ago
Selected Answer: A
Why not A? If he gets full support THEN he'll get the training for the team members. And what is the use of training on Agile if the management then prevents the application of this framework (for example by not granting independence to the team?)
upvoted 6 times
...
Kim222
Most Recent 2 months, 3 weeks ago
Selected Answer: D
This is D
upvoted 1 times
...
Kim222
2 months, 3 weeks ago
Selected Answer: D
Teaching agile to team members is most effective in the immediate and short term. And this is what a PM can do.
upvoted 1 times
...
xcjxcj
10 months, 2 weeks ago
Selected Answer: C
C. Learn as much as possible about the organization Evaluate whether the organization is ready. If just management has this agile thought, it won't be successful.
upvoted 3 times
...
josephsafiran
10 months, 3 weeks ago
Selected Answer: A
The project manager should A. Obtain full management support. Transitioning to an Agile approach is a significant change that affects many aspects of an organization. Having the support of management is crucial for this transition to be successful. Management support can help overcome resistance to change, provide necessary resources, and reinforce the importance of the Agile values and principles throughout the organization.
upvoted 2 times
...
odylec
11 months, 2 weeks ago
Selected Answer: D
Management decided to move to an agile approach and support this idea. So the next step for PM is to train the team
upvoted 2 times
...
Lucky_Cindy
1 year ago
Selected Answer: D
D is correct
upvoted 2 times
...
Only12go
1 year, 1 month ago
Selected Answer: A
To ensure a successful transition from a predictive to an agile approach, the project manager should consider the following actions: A. Obtain full management support
upvoted 1 times
...
Fyrus
1 year, 1 month ago
Selected Answer: A
"Ow, but the company is already transitioning" Yeah, and that doesn't mean that management supports that choice. It's normal to work in a place where the company (C-level people, executive board...) decides something and the workers are not ok with that decision. You first must be sure that everyone is on the same page.
upvoted 1 times
...
balaramch
1 year, 1 month ago
Selected Answer: A
To overcome resistance to change by management
upvoted 1 times
...
kevzzz
1 year, 2 months ago
Selected Answer: D
The company is already transitioning to agile which means, MANAGEMENT approves. The project manager ensures proper agile training for successful agile execution.
upvoted 3 times
...
victory108
1 year, 3 months ago
Selected Answer: A
A. Obtain full management support
upvoted 1 times
...
TONYJAVI
1 year, 3 months ago
Selected Answer: D
The company is already transitioning to Agile so we assume the PM already has support from management
upvoted 3 times
...
SteAle
1 year, 4 months ago
Selected Answer: A
Success strategy # 1 "In order to be successful, management commitment must be secured and in place prior to beginning a program." https://www.pmi.org/learning/library/transitioning-agile-ten-success-strategies-5841
upvoted 2 times
...
ElshRote
1 year, 5 months ago
I guess it's D because the company is already transitioning to agile and that wouldn't have happened without management commitment. That said, the bedrock of agile approach success will then be adequate knowledge among team members, delivered through effective training
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...