exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 332 discussion

Actual exam question from PMI's PMP
Question #: 332
Topic #: 1
[All PMP Questions]

A project manager has been transferred to another country to work on a key project. The project manager successfully completed the planning phase and has started the execution phase, reporting good progress. During the last meeting with the project sponsor, the project manager was told that some stakeholders have complained that the project manager's emails are very harsh.
What should the project manager do to solve this situation?

  • A. Determine the level of influence of the stakeholders who are complaining.
  • B. Change the communication mode from emails to meetings to reduce stakeholders complaints.
  • C. Adjust the communications management plan to gain stakeholder trust.
  • D. Explain to the sponsor that the communication model being used is from company headquarters.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
oenyabine
7 months, 4 weeks ago
I am confused . I would ve thought knowing who complained first then talking to them then adjusting
upvoted 1 times
...
Lucky_Cindy
12 months ago
Selected Answer: C
C is correct
upvoted 1 times
...
victory108
1 year, 2 months ago
Selected Answer: C
C. Adjust the communications management plan to gain stakeholder trust
upvoted 1 times
...
SteAle
1 year, 3 months ago
Selected Answer: C
If the stakeholder finds it harsh, it is worth looking into it and adjusting the style
upvoted 1 times
...
Thirukj
1 year, 4 months ago
Selected Answer: C
C is right
upvoted 2 times
...
AP2023S
1 year, 5 months ago
I don't read anything about trust... they are complaining because the emails are harsh... Maybe talking face to face instead of writing will solve the issue
upvoted 3 times
estimater
12 months ago
agree with you 100%
upvoted 1 times
...
bu02951
1 year ago
it seems like you try to avoid the issue, not to resolve the issue
upvoted 1 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago