Actual exam question from PMI's PMI-PBA
Question #: 154
Topic #: 1
[All PMI-PBA Questions]

A business analyst from Company A has been assigned a project to document and identify requirements for a new commercial software implementation. The first step is to break down the business analysis deliverables into activities and tasks. Then, the business analyst will add an estimate of the time needed to complete the work.
Which type of estimation technique is the business analyst using?

  • A. Analogous
  • B. Bottom-up
  • C. Delphi
  • D. Parametric
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
AlphaD
5 months ago
Selected Answer: B
Bottom up
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.